AWS App Mesh End of Life: September 30, 2026.[¹] New customers locked out since September 24, 2024. Existing customers have 8 months to migrate. Only critical security updates until shutdown.

AWS Official Replacements for App Mesh

  1. ECS Service Connect (for ECS) - AWS-managed mesh without sidecars
  2. VPC Lattice (for EKS) - Application networking across VPCs and accounts
  3. Direct ALB routing - Simplest option for basic use cases

Real-World Migration Case Study

Migrated one production service: App Mesh → Direct ALB

Timeline: ~6 hours total

  • Active migration: 2 hours
  • Troubleshooting: 4 hours

Breakdown:

  • Planning & setup: 30 min
  • Task definition changes: 15 min
  • Service deployment: 20 min
  • Security group fixes: 1 hour
  • Health check troubleshooting: 2 hours
  • ALB configuration: 15 min
  • Testing: 1 hour

Results: Zero downtime. Full App Mesh removal. Instant rollback capability maintained.

Key insight: First service takes 4-6 hours (learning curve). Subsequent services: 1-2 hours each.

Critical Pre-Migration Requirements

Rollback Strategy is Non-Negotiable

  • Ensure all changes are reversible
  • Don't remove App Mesh infrastructure until new setup is validated in production
  • Avoid destructive configuration changes
  • Maintain instant revert capability

Phased Migration Approach

  1. Deploy new configuration alongside existing App Mesh
  2. Test thoroughly without affecting production traffic
  3. Gradually shift traffic to new infrastructure
  4. Validate stability and performance
  5. Remove App Mesh components only after proven success

Common Migration Challenges

Security Groups: Update rules for direct service-to-service communication (no more Envoy proxies)

Health Checks: Reconfigure ALB health checks for direct container access

Service Discovery: Implement AWS Cloud Map or ALB target groups

Migration Resources


Action Required: 8 months until shutdown. Start migration planning now.